Rather than lifting it all at once, the deck was instead separated from all five beams below and lifted first. The two outside beams needing to come out were lifted separately.
“We were now a couple of hours behind, and then it began to rain,” said Mr Wilson, who spent months planning for the bridge replacement along with Wairoa District Council and local contractors and suppliers.
A torrential downpour dogged the five-strong QRS day shift. Rain continued all through the night, making it slow going for the five-strong night shift who worked predominantly on reattaching a new timber deck.
Mr Wilson said just before the road was closed, a woman in labour driven by family members was waved through.
“It was pretty full-on. That situation, along with some challenging issues around fixtures and fittings and a rising river, certainly made for some dramatic moments!”
Mr Wilson says despite the teeming rain and tough working conditions, the QRS staff never complained and instead threw themselves into finishing the bridge replacement ahead of schedule. “They got stuck in, stayed safe and the mood was always great.”
QRS chief executive Nigel Pollock has poured praise on the QRS staff who worked tirelessly to have the bridge reopened on time, ensuring less disruption for the public.
“None of us is as smart as all of us and in this instance the teamwork displayed has led to a speedy safe outcome for everyone. Everyone involved can be very, very proud of their achevement.”
The day shift crew, led by Nick Murray, was Troy Kara, Aperahama Moses, Tui Paikea and Dennis Winiata with help from Gerald Gray, Paul Reedy and Mya Mataki-Wilson. The night shift crew, led by Aaron Munro, was Dudley Story, Steve Ruru, Dason Haapu and Michael McDonald.
QRS learned later that a healthy baby girl was born in Hastings hospital a day after they closed the bridge.